Change of Ownership

Process (Application disposal time is 5 Days)

  1. Submit Application
  2. Clerk ~ 2 Days
  3. Senior Assistant ~ 2 Days
  4. Superintendent ~ 1 Day
  5. Disposal

 

 

Change of Ownership (Death Case Unregistered Will)

Required Documents

  1. Original Death Certificate of the deceased owner. Original to be submitted at concerned authority
  2. Attested Copy of unregistered will
  3. In case, the Will is in a language, other than English, Hindi or Punjabi, a translated copy of the will in English or Punjabi is also be attached.
  4. No objection Affidavits from all left-out legal heirs if the property is bequeathed to one of legal heirs or anyone outside family on basis of will
  5. Affidavits of attesting witnesses in the attached prescribed format.
  6. Clearance of previous mortgage/ Loan/ Redemption Deed
  7. Liability Affidavit of beneficiaries of the Will

 

 

Change of Ownership(Death Case All Legal heirs)

Required Documents

  1. Death Certificate. Original Document to be submitted in Authority
  2. Clearance of previous Mortgage/ Loan/Redemption deed
  3. Legal Heir Certificate. Original to be submitted at Authority.
  4. Any Additional document required for transfer on the basis of succession certificate issued by court
  5. Attach Certified copy of the decree of the Court

 

 

Change of Ownership(Death Case Registered Will)

Required Documents

  1. Certified copy of the Registered Will.
  2. Original Death Certificate of the deceased owner. Original to be submitted at concerned authority
  3. Clearance of previous mortgage/Loan/Redemption deed
  4. In case, the Will is in a language, other than English, Hindi or Punjabi, a translated copy of the will in English or Punjabi is also be attached.
  5. Liability Affidavit of beneficiaries of the Will

 

Issuance of CD

Process (Application disposal time is 15 Days)

  1. Submit Application
  2. Clerk ~ 4 Days
  3. Senior Assistant ~ 5 Days
  4. Assistant Estate Officer ~ 3 Days
  5. Estate Officer ~ 3 Days
  6. Disposal

 

Issue of No Due Certificate

Process (Application disposal time is 5 Days)

  1. Submit Application
  2. Record Keeper ~ 1 Day
  3. Sr. Assistant (Accounts) ~ 3 Days
  4. Account Officer ~ 1 Day
  5. Disposal

 

Issue of Re-allotment Letter.

Required Documents

  • Transfer permission before CD. Original to be submitted at Authority (Applicable only if issued Manually)

 

 

Permission for Sale/Gift/Transfer

Process (Application disposal time is 10 Days)

  1. Submit Application
  2. Clerk ~ 3 Days
  3. Senior Assistant ~ 4 Days
  4. Superintendent ~ 3 Days
  5. Disposal

 

 

Permission to Mortgage

Process (Application disposal time is 7 Days)

  1. Submit Application
  2. Clerk ~ 2 Days
  3. Senior Assistant ~ 3 Days
  4. Superintendent ~ 2 Days
  5. Disposal

 

Permitting Professional Consultancy Services

Process (Application disposal time is 10 Days)

  1. Submit Application
  2. Clerk ~ 3 Days
  3. Senior Assistant ~ 4 Days
  4. AEO ~ 3 Days
  5. Disposal

 

Transfer of Letter of Intent

Process (Application disposal time is 21 Days)

  1. Submit Application
  2. Clerk ~ 2 Days
  3. Senior Assistant ~ 3 Days
  4. AEO ~ 2 Days
  5. Estate Officer ~ 3 Days
  6. Disposal

 

Transfer Permission (Before CD)

Required Documents

  1. Affidavit from the Seller(s) that the property is free from all sorts of encumbrances or litigation in any court of law, liens, mortgage etc
  2. Liability affidavit of Purchaser(s) / Doner(s) / Transferee(s)
  3. Photo Identity Proof of Seller(s)
  4. Original letter of Allotment / Re-allotment letter . Original to be submitted at Authority
  5. Clearance against loan / mortgage (if applicable)
  6. Self attested copy of sanction of Sewerage Connection / Occupation Certificate , if obtained
  7. Photo Identity Proof of Purchasers

 

Demarcation of Plot

Required Documents

  1. Photocopy of Proof of ownership
  2. Photocopy of the forwarding letter regarding sanction of building plan by empanelled architect. Or issued by Estate Officer
  3. Any other supporting document

 

Issue of Completion Certificate/ Occupation Certificate

Required Documents

  1. Certificate of completion by empanelled Architect, of Authority as per list of empanelled Architects.
  2. Photographs of the completed building, to be pasted on the blank pages and duly attested by empanelled Architects
  3. Notice of completion & permission to occupy, as prescribed under rule 10(1) of the building rules along with a declaration by the owner.
  4. Mining certificate
  5. Any other supporting document
  6. Fire safety certificate for commercial property
  7. Structure stability certificate
  8. Undertaking by owner with photograph

 

Issue of DPC Certificate

Required Documents

  • Photocopy of Demarcation Certificate (In case of allotment by GMADA)
  • Upload DPC certificate issued by Empaneled Architect ,as applicable
  • Any Other supporting document
  • Clearance/NOC of previous Loan (If applicable)
  • Regularisation of Water connection

 

Process (Application disposal time is 7 Days)

  • Submit Application
  • Clerk ~ 2 Days
  • Junior Engineer ~ 2 Days
  • Superintendent (Single window) ~ 1 Day
  • Disposal

 

Sanction of Sewerage Connection

Process (Application disposal time is 7 Days)

  1. Submit Application
  2. Clerk ~ 1 Day
  3. Junior Engineer ~ 2 Days
  4. Superintendent (Single window) ~ 1 Day
  5. Disposal

 

Sanction of Water Supply

Process (Application disposal time is 7 Days)

  1. Submit Application
  2. Clerk ~ 1 Day
  3. Junior Engineer ~ 2 Days
  4. Superintendent (Single Window) ~ 1 Day
  5. Disposal

 